It was 2019 and in the Paparoa Track’s new Pororari Hut, track builder Barry Gordon was enthusing about swales. The track was still under construction and I’d been invited for a sneak peep of what had been done so far.
For water management, swales are the best new things, said Gordon.
“Swales are where you move the track around a bit with natural humps and hollows, and change the camber from in-slope to out-slope every 10 metres or so and the water just runs off,” he explained. “It means no invasive side drains that need maintenance to keep from blocking up, and no water running on the track, eroding it away. If we do need a culvert, in extra wet places, we hide it so you won’t see it, just like we’re rehabbing the trackside vegetation so the track isn’t intrusive.”
Rehabilitation was a contract condition, he says. “We only cut, prune or blast what we absolutely need to, then one of the crew follows the digger like a gardener, restoring the vegetation so the track looks like it’s always been there.”
It’s true, I decided, the next day as I followed the fern-lined trail, threading like a silver ribbon through the bush. No ugly digger scars to see here.
Gordon was working for WestReef Services, one of the companies contracted by DOC to build the new dual-use walking/biking Great Walk. Metre by metre, their saws and diggers and ‘gardeners’ followed bits of pink tape, tied to trees and rocks, up and over the Paparoa Range. The tape marked the route set by track design guru Hamish Seaton, who combined LIDAR aerial imaging, computer modelling and not a little bit of bush bashing to determine the most environmentally sensitive, consistently graded and feasible way to go.
Swales, ‘rehabbing’, specialised track building companies, aerial imaging and computer modelling epitomise the new approach to track building. But it’s not all about technology. Going back to the basics of heritage track building was an essential part of the Paparoa Track’s planning and design, says DOC project manager, Mark Nelson.
“Paparoa was the mechanism for taking a whole bunch of ideas from the past and learning from them,” Nelson says. “We spoke to experienced track men, for example Ken Bradley, about what worked in Fiordland, and Phil Rossiter from the Old Ghost Road.”
Ken Bradley recently retired with a QSM for services to conservation. He says most of Fiordland’s original tracks, like the Dusky, were simply surveyed then cut, using axes, slashers and crosscut saws, and the surface was the forest floor. The next stage was the early pack tracks that needed a better surface.
“It was hard labour, all picks and shovels,” he says.
That changed in the 1980s when the Kepler Track became the first track built from scratch by mechanical digger.
“We probably wouldn’t have got the go-ahead for diggers if it wasn’t for a massive slip in the Iris Burn,” Bradley says. “The bosses figured we couldn’t do any more damage than what nature itself had done.
“Once we crossed the slip we just kept going, building a two-metre wide track to the new Iris Burn Hut and that proved beyond all reasonable doubt diggers were the way to go.
“The early concern was that a digger would make too much environmental impact; in fact, they created far less. A digger could pull out an entire shrub or little tree and place it aside for replanting later. And a digger never got tired.”
Mechanical barrows for carting metal were another Kepler first, says Bradley. “Initially, we had little ability to cart metal. We were restricted by how far and how steep you could push a wheelbarrow. So we leased newly imported Honda barrows. Since then, hundreds of them have been used around the country; so with the barrows and the digger, we revolutionised track building.”
Since the Kepler, more knowledge of track building has been gained, says Bradley, citing the use of swales. “Water is the big destroyer of tracks and side drains need to be kept clean, there’s a lot of shovel work involved. If I was building the Kepler again, I’d use swales.”
Swales have now been used on the Queen Charlotte Track, adds Roy Grose, who has worked on tracks in Tongariro and the Marlborough Sounds over the past 30 years.
Don’t forget the leaf blower
One night in April this year, in Pororari Hut, someone complained about bugs in the toilets. The warden said no worries, he’d blast them away with his leaf blower. Leaf blower? It’s for track maintenance, he laughed.
It’s true. DOC’s Mark Nelson confirms that a leaf blower is one of the most important tools for maintaining the Paparoa Track. “If you have leaf litter on the track and water runs across, it can create a little dam, then the water starts to wash out the track. So in the long term, using the leaf blower saves the maintenance crews a huge amount of work.
“It represents the changing face of the technology of track building and maintenance.”

